Major works modernising the railway between Morley and Dewsbury have taken the Transpennine Route Upgrade a step closer to delivering faster, more frequent trains on a more reliable and greener network across the North.
A 28-day intensive period of construction at Batley and Dewsbury stations has concluded, marking significant progress in the broader Transpennine Route Upgrade project. The initiative aims to facilitate faster, more frequent, and more reliable train services across the north, while also transitioning toward a greener, fully electrified rail network.
Central to the project was the renewal of over five kilometers of track and the installation of more than 800 meters of new drainage systems, which will improve the reliability of train services in the region by reducing the risk of flooding.
Additionally, the Jacks Lane bridge was replaced, allowing for the passage of larger and faster trains.
Extensive work was completed at both Batley and Dewsbury stations to enhance passenger experience. Both stations now feature upgraded facilities, including strengthened footbridges and extended roof canopies. Platform extensions were also carried out at Dewsbury to accommodate longer trains with increased seating capacity. Furthermore, overhead line equipment masts were installed with new foundations, clearing the path for the future integration of electric train services.
Related stories
With the current phase of the upgrade nearing completion, accessibility improvements remain a priority. New lifts are being installed at Batley station, with completion expected later this year to ensure step-free access for passengers. These enhancements reflect the project's commitment to modernization and improved service standards.
Following this successful milestone, the Transpennine Route Upgrade team has shifted its focus to Huddersfield station. A series of weekend works are scheduled throughout July and August to prepare for a 16-day program of improvements slated for September. During these upcoming works, diverted routes and rail replacement buses will ensure continued passenger service on weekdays, while weekend operations will focus on roofing, platform extensions at the station's lead end, and lift installations. Currently, 25 percent of the Transpennine route has been successfully electrified.